Tag: development

SayPro is a Global Solutions Provider working with Individuals, Governments, Corporate Businesses, Municipalities, International Institutions. SayPro works across various Industries, Sectors providing wide range of solutions.

Email: info@saypro.online Call/WhatsApp: Use Chat Button 👇

  • SayPro Diepsloot Youth Project …ESOR CONSTRUCTION ON TRACK WITH TWO PEDESTRIAN BRIDGES AT DIEPSLOOT INTEGRATED HOUSING AND INFRASTRUCTURE DEVELOPMENT

    Esor Construction, through subsidiary Safdev Tanganani, is the turnkey contractor and developer of a R2 billion integrated housing and infrastructure development in Diepsloot, Johannesburg. The 237 ha project will ultimately see the construction of 9 000 houses of various typologies and tenure options,  three  schools,  five  multi-­‐functional  nodes,  three  shopping  centres,  five  neighbourhood parks, a magistrate’s court and a hospital. “We started constructing two landmark and iconic pedestrian bridges across William Nicol Drive to the value of R52 million in July 2013. These bridges form part of the bulk infrastructure for the development and will link the current Diepsloot to the new,” Duncan says.

     

    “Currently we are utilising our civils capabilities for the two pedestrian bridges while our building skills will be deployed for some of the top structures. There is not a single free standing top structure in the entire development as everything will be either semi-­‐detached or multi-­‐storey units. In fact the bulk of it will be three storeys, making it one of the highest density integrated developments in Gauteng at the moment. That is the way that designs are moving and is inevitable given the extreme shortage of well located land and the exorbitant costs of providing bulk services.” Duncan adds that Diepsloot has been classified as one of the top seven National Priority Projects in South Africa at present.

     

    “We manage all the sub contractors, whether electrical, civils or building, while the professional team at this stage is managed by Gauteng Province through its appointed Project Manager. Another requirement from Province is that 30% of the work by value has to be undertaken by local resources.” Duncan says that Esor Construction brings in the necessary supervisory skills and then deploys small focused teams to acquire skills as they carry out the actual work. However, the pedestrian bridges are challenging monolithic structures that are being built largely without the involvement of smaller contractors. “The pedestrian bridges presented an engineering challenge in that it is tricky and difficult work undertaken at a substantial height over a major road.”

     

    The presence of threatened giant African bullfrogs on site has necessitated onerous requirements in terms of the environmental management plan. “The idea is that as we start building on site, through

     

    some ‘structured coercion’ the bullfrogs will migrate down to the vlei portion of the site that has been designated as a wildlife reservation for their preservation.” Due to the extent of the project it has also not been decided yet as to whether or not the infrastructure and housing components should be tackled jointly or separately. “From a contractor’s perspective it will be wonderful just to complete the infrastructure for the entire development before building the first house.”

     

    Duncan says the South African housing market is showing green shoots at present. “We are still sitting with a very under supplied market especially on the affordable housing side. There are signs of growth in that projects are being kick started and the banks are lending again. The government also has to deliver in terms of its national housing budget.” Looking at some of the latest trends in the housing sector, Duncan says that the Diepsloot development will incorporate a large number of so called CRUs or Community Rental Units in order to cater for the bottom end of the market. “Rental is becoming a bigger and bigger component of the affordable and subsidised housing markets.”

     

    Duncan concludes that the Diepsloot project is a landmark integrated development not only for Gauteng but for South Africa as a whole. “It is developments such as these that are advancing the affordable and subsidised housing markets in the country. There are a number of trends being pioneered at Diepsloot, such as the Total Street Concept, where the entire road servitude is paved in order to accommodate pedestrian walkways and cycle and traffic lanes. “Such extensive blacktop is more expensive but it is a far better concept in terms of urban planning as it definitely enhances the living space of the residents.” Duncan adds that the fully subsidised housing units at Diepsloot will feature insulation and even double glazing, in addition to a 20 m2 rental unit attached to each 40 m2 house to order to create micro landlords and help generate additional income for residents.

     

    DIEPSLOOT 01: The North Bridge taking shape over William Nicol Drive near Diepsloot. DIEPSLOOT 02: The iconic ‘bird wing’ structures can be seen on the South Bridge.

  • SayPro Diepsloot Youth Project …HERITAGE IMPACT ASSESSMENT FOR THE PROPOSED DIEPSLOOT PEDESTRIAN BRIDGE DEVELOPMENT, RANDBURG MAGISTERIAL DISTRICT, GAUTENG PROVINCE

    A small, unnamed stream, a tributary of the Jukskei River, passes through the Diepkloof settlement, dividing the community in two. At present, only a few formal crossings allow access to the opposite sides. These are single lane, low water bridges, with limited access for pedestrians. In summer, many of these crossings become flooded, creating a dangerous situation if people want to cross to the other side. Therefore the Johannesburg Development Agency plans to build a proper, safe, crossing for pedestrians to use.

     

    In accordance with Section 38 of the NHRA, an independent heritage consultant was appointed by Envirolution Consulting to conduct a Heritage Impact Assessment (HIA) to determine if any sites, features or objects of cultural heritage significance occur within the boundaries of the area where it is planned to develop the project.

     

    • As no heritage sites occur in the study area, there would be no impact resulting from the proposed

     

    Therefore, from a heritage point of view we recommend that the proposed development can continue. However, we request that if archaeological sites or graves are exposed during construction work, it should immediately be reported to a heritage practitioner so that an investigation and evaluation of the finds can be made.

  • SayPro Diepsloot Youth Project …HERITAGE IMPACT ASSESSMENT FOR THE PROPOSED DIEPSLOOT PEDESTRIAN BRIDGE DEVELOPMENT, RANDBURG MAGISTERIAL DISTRICT, GAUTENG PROVINCE

    A small, unnamed stream, a tributary of the Jukskei River, passes through the Diepkloof settlement, dividing the community in two. At present, only a few formal crossings allow access to the opposite sides. These are single lane, low water bridges, with limited access for pedestrians. In summer, many of these crossings become flooded, creating a dangerous situation if people want to cross to the other side. Therefore the Johannesburg Development Agency plans to build a proper, safe, crossing for pedestrians to use.

     

    South Africa’s heritage resources, also described as the ’national estate’, comprise a wide range of sites, features, objects and beliefs. However, according to Section 27(18) of the National Heritage Resources Act (NHRA), Act 25 of 1999, no person may destroy, damage, deface, excavate, alter, remove from its original position, subdivide or change the planning status of any heritage site without a permit issued by the heritage resources authority responsible for the protection of such site.

     

    In accordance with Section 38 of the NHRA, an independent heritage consultant was appointed by Envirolution Consulting to conduct a Heritage Impact Assessment (HIA) to determine if any sites, features or objects of cultural heritage significance occur within the boundaries of the area where it is planned to develop the project.

     

  • SayPro Diepsloot Youth Project HISTORY OF DEVELOPMENT CONTRIBUTIONS IN SOUTH AFRICA

    The use of DCs in South Africa can be traced back to the 1930s. However, municipalities in SA have applied DCs inconsistently and have often not followed the guiding principles described above. This dynamic has resulted in both a severe under-collection of funds by municipalities and resistance and frustration by the real estate developer community. Whilst the national Spatial Planning and Land-use Management Act (2013) makes specific provision for the use of DCs by local authorities, it does not specify how the DCs should be calculated and it contains several definitions that are inconsistent with other relevant legislation. As a result, in 2017, the South Africa National Treasury initiated several legislative changes and prepared draft guidelines for the standardization, development and implementation of such charges at a local level.

     

    Although these legislative and policy amendments are still being finalised, several municipalities, such as the City of Johannesburg, have begun implementing DCs policies that attempt to be in line with these pending legal changes and guidelines.

    A review of the Diepsloot case shows how DCs have been used in this fluid legislative environment to successfully fund infrastructure development that benefits a wider geographic area. This case review also highlights implementation challenges and how these were, or could be, overcome.

  • SayPro Diepsloot Youth Project THE APPLICATION OF DEVELOPMENT CONTRIBUTIONS IN THE DIEPSLOOT NODE

    Although there was market demand for a range of commercial and residential uses in the Diepsloot Node, the lack of bulk infrastructure constrained developers from building projects that could meet this demand. Furthermore, attainment of required land use and development approvals from local government authorities was preconditioned upon these infrastructure constraints being addressed. This problem was exacerbated  by the fact that the various local government authorities had insufficient capital budgets to build the necessary infrastructure upfront, even if the costs could be recouped through payment by developers of DCs over time.

     

    Specifically, several types of bulk infrastructure needed to be installed to make the developments possible. Firstly, the R511 provincial road had to be expanded. This was funded through a partnership arrangement involving the provincial road authority and two of the developments in a two thirds/ one third ratio. However, as DCs do not apply to provincial infrastructure, the two developments could not off-set their contribution towards this infrastructure against any DCs that they were required to pay the local authority to get the necessary rights to develop the sites.

     

    Similarly, each of the three developments had to fund and build electrical sub-stations on their respective sites. As the electrical supply authority was a national state-owned enterprise – Eskom, they similarly could not offset these costs against any DCs demanded by the local authorities.

     

    Other key pieces of urban infrastructure necessary to unlock the developments included a water reservoir, a sewer pump station and the upgrade of several municipal roads.

     

    The water reservoir was funded by a combination of two of the developments, but both developments were able to off- set these costs against the DCs required by the municipality for this bulk infrastructure type. The sewer pump station was funded by a different combination of two of the

    developments and similarly were able to off-set these costs against the required municipal DCs. It appears that all three developments recognised the need to share the burden of collectively providing this key infrastructure upfront.

     

    In addition, the different developments had to build and upgrade several municipal roads. Although they were able to off-set these against the DCs owed to the municipality, they could not off-set the total cost incurred. One of the developers argued that this was because the capital unit cost (as discussed in 5.1 above) was incorrectly calculated by the municipality such that the actual cost was 2 – 3 times higher than what was charged in terms of the DCs. Hence, by building the infrastructure upfront in lieu of DCs, the developers incurred higher costs that had to be borne by the development.

     

    The calculation of the capital unit cost raises some debate. In the City of Johannesburg, the actual cost of the infrastructure provided by the developer is used in determining the amount that can be off set against the DCs (as per option 1 in Table 1) . Whilst this can be more accurate, it can be administratively cumbersome and can result in protracted negotiations, the outcomes of which can be difficult to predict and hence to factor into the viability study of the development.

     

    Other municipalities, such as the Municipality of Tshwane, apply a standard unit cost rate (as per option 4 in Table 1) regardless of the actual costs, which may differ substantially depending on the local conditions. For example, the costs to develop a road may be lower if the required material is nearby, but equally may be higher if a bridge needs to be constructed due to the topography. However, it was felt that over time it balances out – “you win on one project and lose on another” as one developer said. Furthermore, this approach was seen by the developers to be simpler, quicker and more predictable.

     

     

     

     

     

    In addition, the upfront development of the bulk infrastructure by the developers raised the issue discussed in 6.7 above. In some instances, the bulk infrastructure had to be delivered at a scale that was greater than what was needed by the developments (for example, an electrical sub-station comes in standard sizes and hence additional capacity beyond the requirements of the developments was provided). This raised two problems:

     

    Firstly, the cost of this additional capacity was high, putting pressure on the developments to bear these costs upfront. Secondly, a mechanism needed to be put in place for the developers to recoup the cost of the excess capacity over time. In this case the City of Johannesburg did not have a mechanism in place for this to happen and therefore an additional burden was placed on the developments.

     

    A possible solution may have been to apply the City of Tshwane policy, which allows the cost of any excess

    capacity provided by the developer to be recouped through the future DCs paid by subsequent developments that utilise this capacity. In this case, the developer providing the excess capacity would enter into a service level agreement, whereby the municipality would pay the developer the DCs paid to it by the subsequent developers.

     

    This agreement would usually be limited to a time period of 5 – 10 years and therefore the initial developers would run the risk that no subsequent development takes place. Notwithstanding this, this approach was seen by the developers to be more equitable and viable.

     

    Though complicated to execute, the funding of key bulk water, sewer and road infrastructure using DCs enabled commercial centres and over 30 000 houses, of which 4500 were affordable, to be developed in the area.

     

     

  • SayPro Diepsloot Youth Project Diepsloot Development

    Newtown Landscape Architects cc were appointed by SafDev Tanganani (Pty) Ltd to conduct an

    Environmental Impact Assessment (EIA) for the proposed establishment of Diepsloot East Residential Development on Portions RE/2 and 123 of the farm Diepsloot 388 JR, City of Johannesburg Metropolitan Municipality (City of Joburg). During the Environmental Impact Assessment (EIA) phase there were however changes as the project became a more critical and urgent project. The Gauteng Department of Local Government and Housing (GDLGH), now known as the Gauteng Department of Human Settlement (GDHS) approached SafDev Tanganani (Pty) Ltd and an agreement was reached that the GDHS will buy the property from SafDev Tanganani (Pty) Ltd and will take over the project. Emba PM was appointed as the Project Management Team and Metroplan were appointed as the Town Planners. In 2012 a new Project Management Team, NANZA Consulting, was appointed. Due to the appointed of a new Project Management Teams and town planner as well as environmental concerns there were changes to the layout of the development. This will be discussed in detail under Section 4.

     

    The proposed project was registered with the Gauteng Department of Agriculture and Rural Development (GDARD) under the National Environmental Management Act (Act 107 of 1998), Environmental Impact Assessment Regulations 2006. Since 2006 the Environmental Impact Assessment Regulations changed and therefore a new application was submitted according to the Environmental Impact Assessment Regulations 2010. The proposed activities to be undertaken are listed activities in terms of Government Notice R661 and R662 of 30 July 2010 and it requires that environmental authorisation be applied for. The following Activities were applied for:

     

     

    Government Notice No. R661:
    Activity 9 The construction of facilities or infrastructure exceeding 1000 metres in length for the bulk transportation of water, sewage or storm water

    i.             With an internal diameter of 0.36 metres or more; or

    ii.             With a peak throughput of 120 litres per second or more, Excluding where:

    a)      Such facilities or infrastructure are for bulk transportation of water, sewage or storm water or storm water drainage inside a road reserve; or

    b)      Where such construction will occur within urban areas but further than 32

    metres from a watercourse, measured from the edge of the watercourse.

    Activity 11 The construction of:

    i.             Canals

    ii.             Channels

     

     

     

      iii.             Bridges

    iv.            Dams

    v.            Weirs

    vi.            Bulk storm water outlet structures

    vii.            Marinas

    viii.            Jetties exceeding 50 square metres in size

    ix.            Slipways exceeding 50 square metres in size

    x.            Buildings exceeding 50 square metres in size

    xi.            Infrastructures or structures covering 50 square metres or more Where such construction occurs within a watercourse or within 32 metres of a watercourse, measured from the edge of a watercourse, excluding where such

    construction will occur behind the development setback line.

    Activity 18 The infilling or depositing of any material of more than 5 cubic metres into, or the dredging, excavation, removal or moving of soil, sand, shells, shell grit, pebbles or rock from

    i.             A watercourse

    ii.             The sea

    iii.             The seashore

    iv.            The littoral active zone, an estuary or a distance of 100 metres inland of the high water mark of the sea or an estuary, whichever distance is greater

    But excluding where such infilling, depositing, dredging, excavation, removal or moving

    a)      Is for maintenance purposes undertaken in accordance with a management plan agreed to by the relevant environmental authority; or

    b)      Occurs behind the development setback line.

      c)
    Government Notice No. R662:
    Activity 15 Physical alteration of undeveloped, vacant or derelict land for residential, retail, commercial, recreational, industrial or institutional use where the total area to be transformed is 20 hectares or more;

    Except where such physical alteration takes place for

    i.             Linear development activities; or

    ii.             Agricultural or afforestation where activity 16 in this Schedule will apply.

     

    The methodology used for the assessment was to investigate all environmental issues associated with the project. Environmental assessment procedures followed so far, according to the National Environmental Management Act, 1998 (Act 107 of 1998) as amended and the Environmental Impact Assessment Regulations, 2010 are:

    • Submission of an application form on 6 July

     

     

     

    • Statutory advertising on site, 12 July
    • Advertising in a local newspaper. The advertisement was placed in The Star on 12 July 2007.
    • Public Participation, the purpose of which is to inform all relevant I&APs by means of a Public Meeting. The meeting was held on 13 September
    • Circulation of the Draft Scoping Report to all registered I&Aps.
    • Submission of the Scoping Report to GDARD on 30 January
    • GDARD authorization was received on 9 January 2009 to proceed with the EIA
    • The Public Participation Process for the EIA phase included the notification to I&APs of comments received from GDARD on the Scoping
    • GDARD’s comments on the Scoping Report were sent to registered I&APs on 2 February 2009.
    • A meeting with the Councillors, Home Owner Associations (HOA) and Conservancies was held on 24 November 2009 to discuss the changes in the layout as well as the change in ownership of the
    • A Public Meeting was held on 30 November 2010 and a follow up meeting was held on 22 February 2011. Another follow up meeting was held on 15 March
    • Re-submission of the Application according to the Environmental Impact Assessment Regulations 2010 on 26 July
    • Re-advertising the project:
      • On site – 6 September 2013
      • Local Newspapers
        • Fourways Review – 5 September 2013
        • Midrand Reporter – 4 September 2013
      • Notifications to Stakeholders and I&APs – 4 September 2013
    • The Draft EIA Report was send to all registered I&APs, stakeholders and State Departments.
    • A Public Meeting will be held to discuss the EIA Report either the last week of September 2013 or the first week of October 2013. The date will however be
    • The Final EIA Report will be circulated to all registered I&APs before submission to GDARD.
  • SayPro Diepsloot Youth Project LEGAL REQUIREMENTS OF THE PROPOSED DEVELOPMENT

    Environmental Impact Assessment process, which includes a Scoping study, is required by legislation. The process ensures that all relevant information is presented in order to facilitate good management decision-making. The legislations that require development projects to undergo through the Scoping / EIA Process are:

     

    • National Environmental Management Act (act 107 of 1998) as amended: This Act requires that the report concerning the impact of the proposed development on the environment be prepared. There are certain activities that are listed as activities that require EIA process. These activities are listed in Government Notice R386 and R387, 21 April 2006. The proposed development, which is the rezoning of “Undetermined” land into residential, is listed under Activity 2 (R387). Please note that although there are new Regulations (NEMA 2010) the proposed project falls under the NEMA 2006 Regulations as the application was submitted during the period of the NEMA 2006 Regulations. Therefore the processes followed are as per the NEMA 2006 Regulations and not the NEMA 2010
    • Constitution of the Republic of South Africa (Act 108 of 1996): Section 24(b)(i) encourages prevention of pollution and ecological degradation. Section 24(b) (iii) promotes ecologically sustainable
    • National Heritage Resource Act of 1999 (Act 25 of 1999) (NHRA): Section 34, no person may alter or demolish any structure or part of a structure, which is older than 60 years without a permit issued by the relevant provincial heritage resources authority (SAHRA).
    • The National Water Act (Act No 36 of 1998).
    • National Environmental Management: Waste Act 2008 (Act 59 of 2008)
    • The National Environmental Management Biodiversity Act, 2004 (Act No.10 of 2004).

     

     

    The following policies and guidelines were consulted:

    • From the NEMA Environmental Impact Assessment Regulations Guideline and Information Document Series the following guidelines were used:
      • Guideline on Public Participation in the Environmental Impact Assessment Process (October 2012)
      • Draft Guideline on Need and Desirability in Terms of the Environmental Impact Assessment (EIA) Regulations, 2010 (October 2012)
      • Guideline on Alternatives (August 2010)
    • GDARD requirements for Biodiversity Assessments (2008 & 2012)
    • City of Johannesburg Spatial Development

     

  • SayPro Diepsloot Youth Project Diepsloot East Residential Development – section to the north of the wetland

    In order to service the high laying portion of the Diepsloot East Residential Development, located north of the wetland, as well as future developments located in the area to the west of the proposed site, it is proposed that a new DN 375 bulk main and 1600kl tower be constructed.

     

    In the meantime, while the reservoir, tower and bulk pipe line are still planned, a temporary connection to the existing DN600 Johannesburg Water (JW) pipe line will be proposed. This pipe line runs along the wetland area on the northern part of the property.

  • SayPro Diepsloot Youth Project Diepsloot East Residential Development – section to the south of the wetland

    In order to service the southern section of the proposed development it will be necessary to construct the reservoir with a DN325 connection to the existing DN600 pipe line. A secondary connection to the Dainfern bulk pipe line (to be constructed within the next 2 years) is proposed to establish a ring feed to the existing DN 600 Diepsloot bulk pipe line.